BLM opens public comment on Western Gateway fuel pipeline into Arizona

The federal environmental review covers a proposed gasoline and diesel line that would enter the state along I‑10 and run through Casa Grande to Buckeye. Two virtual meetings are set for early December.

2 min read
Email

What to know

  • The Bureau of Land Management has started an environmental review of the proposed Western Gateway Fuel Pipeline and opened a public comment period.
  • KJZZ reported that comment closes in 30 days and that BLM will hold two virtual community meetings in early December.
  • In Arizona the route would follow Interstate 10 from New Mexico, run north of Tucson, pass through Casa Grande and reach Buckeye.
  • The companies behind the project are targeting a 2029 completion, subject to permits and regulatory approvals.

The federal government has begun an environmental review of a proposed pipeline that would carry gasoline and diesel into Arizona, and the public now has 30 days to weigh in, KJZZ reported Tuesday.

According to KJZZ, the Bureau of Land Management plans two community meetings in early December, and both will be held online. The station's report did not give the meeting dates, the comment deadline as a calendar date or the address for submitting comments.

What the pipeline would do

The Western Gateway Fuel Pipeline would move refined fuel from the mid-continent and Gulf Coast regions, KJZZ reported, and it put the length at almost 887 miles. In Arizona, the line would enter from New Mexico along Interstate 10, pass north of Tucson and go through Casa Grande before reaching Buckeye.

The proposal also includes supporting construction, such as access roads and pump stations, according to KJZZ.

The companies say the system would give Arizona a new fuel supply route. Kinder Morgan's project page says the wider system would create a fuel supply path from St. Louis and expanded Gulf Coast points to Arizona and California. KJZZ does not name the companies; the project page describes a new pipeline from Borger, Texas, to Phoenix under the same Western Gateway name.

Who is behind it

Phillips 66, Kinder Morgan and HF Sinclair announced a joint venture agreement and a final investment decision on Aug. 11, according to Kinder Morgan. The companies describe a 1,300-mile system. It includes an approximately 900-mile new pipeline from Borger, Texas, to Phoenix, which Phillips 66 would build and operate. KJZZ put the new pipeline at almost 887 miles; the companies describe it as approximately 900 miles.

Kinder Morgan would also contribute its existing SFPP East Line, which runs from El Paso, Texas, to Phoenix and Tucson. Its SFPP West Line, which runs from Colton, California, to Phoenix, would be reversed so fuel can flow west into California.

The Oil & Gas Journal reported that Phillips 66, Kinder Morgan and HF Sinclair would own 49.9%, 35.1% and 15% of the venture. It said the system is designed for an initial capacity of 230,000 barrels a day, with the project carrying an enterprise value of about $5 billion.

"This project brings together strategic supply access, existing infrastructure and experienced operators to improve affordability and assurance of supply for customers in the Western United States," Kinder Morgan CEO Kim Dang said, according to the Oil & Gas Journal.

What happens next

Kinder Morgan said the partners aim to finish the system in 2029 if all permits and regulatory approvals come through. The BLM review is one step in that process. KJZZ reported that public comment closes in 30 days, and the two virtual meetings are set for early December.

Sources

Links to the reporting and records this story is based on.

  1. KJZZBLM opens public comment on 900-mile gas pipeline from north Texas to ArizonaNov. 17, 2026
  2. Kinder MorganWestern Gateway Pipeline Project
  3. Oil & Gas JournalPhillips 66, Kinder Morgan, HF Sinclair sanction Western Gateway pipelineAug. 12, 2026