Arizona lawmakers press Army Corps to hold Rio de Flag contract deadline after deadly floods
Flagstaff's $244 million flood control project, authorized in 2000, is meant to protect about 1,500 Southside structures. Two people died in flooding this month.

What to know
- Sens. Mark Kelly and Reuben Gallego and Reps. Greg Stanton and Elijah Crane cosigned a letter urging the Army Corps to prioritize the Rio de Flag project.
- The letter asks the Corps to meet its planned March 2027 deadline for awarding the construction contract.
- The project cost is currently evaluated at $244 million, with Flagstaff paying 35% and the Army Corps federal funds covering the rest.
- Extreme rainfall caused two deaths and extensive property damage in Flagstaff earlier this month, KJZZ reported.
FLAGSTAFF, ARIZ. — Arizona's two U.S. senators and two members of the U.S. House are asking the Army Corps of Engineers to keep to its March 2027 deadline for awarding the construction contract on Flagstaff's long-delayed Rio de Flag flood control project, KJZZ reported.
Sens. Mark Kelly and Reuben Gallego cosigned a letter with Reps. Greg Stanton and Elijah Crane that demands the project be prioritized, according to KJZZ. The letter called the improvements "an immediate public safety necessity."
The push follows flooding earlier this month. Extreme rainfall caused two deaths and extensive property damage in Flagstaff, KJZZ reported. The project aims to prevent damage to approximately 1,500 structures in a vulnerable flood plain in the city's Southside neighborhood by redirecting the Rio de Flag watershed.
An Associated Press photo published with KJZZ's story shows a pedestrian crossing a flooded Flagstaff road on Sunday, Nov. 1. A related item on KJZZ's site, about Southside residents starting cleanup, says a storm that hovered over Flagstaff one weekend flooded homes, businesses and streets in that neighborhood.
City leaders also met with the Army Corps in Washington, D.C., and asked that the project not be delayed further, according to KJZZ. KJZZ's report did not include a response from the Army Corps to the letter or the city's request.
Cost and history
The project cost is currently evaluated at $244 million, KJZZ reported. Flagstaff is paying 35% of that out of pocket, and federal funds from the Army Corps cover the rest. The city has already spent $12.5 million on smaller resilience features.
Flagstaff Mayor Becky Daggett said the project got its first authorization in 2000, under the Water Resources Development Act. As estimated costs ballooned over the years, KJZZ reported, the project had to be re-authorized twice. KJZZ described the proposals as more than 25 years old.
Daggett said, "as the project has increased in price, that's when we've had to do some extra work to get that federal money assigned to address the cost increases."
She said the city has held up its end. "The city has done everything that we've needed to do- and that includes purchasing land from the BNSF railroad and purchasing private property along where the new channel of the Rio de Flag will flow," Daggett said.
I know this is a complex project, but I'll keep emphasizing that we cannot afford one more delay. We have to get started next year, and get this project finished as soon as possible.
Daggett also said she appreciates the senators and Crane for recognizing how critical the project is, and thanked BNSF and the Army Corps. The next marker is the Corps' planned March 2027 deadline to award the construction contract.