Cochise County chair details SpaceX's grid and water promises for $50 billion data center
Supervisors Chair Frank Antenori says SpaceX will use no groundwater to run it and will put $3.6 billion into the grid, as Attorney General Kris Mayes presses for a delayed vote.
What to know
- Supervisors Chair Frank Antenori said SpaceX pledged $3.6 billion for grid upgrades, no groundwater use and county dark-sky compliance.
- Antenori said the campus could bring about 1,000 jobs at full build-out; a researcher called his 1,500 secondary jobs high.
- Attorney General Kris Mayes says the campus would draw 6 gigawatts at full build-out and wants the county to delay its vote.
- The Planning and Zoning Commission is scheduled to take up the permit Dec. 9; Mayes holds a town hall Dec. 3.
WILLCOX, ARIZ. — SpaceX has said it will run its proposed Cochise County data center without groundwater and has pledged $3.6 billion for power grid upgrades, Board of Supervisors Chair Frank Antenori said, AZFamily reported Friday. He said the company will also follow the county's dark-sky rules.
His account comes as Arizona Attorney General Kris Mayes urges the county to put off its vote. According to Mayes, the finished campus would draw 6 gigawatts, nearly 20% of the state's total power-generating capacity, AZFamily reported. The outlet said that demand is part of why her office wants the delay.
The stakes reach well past Willcox. SpaceX announced plans this month to build the state's largest data center campus, AZFamily reported, and several community groups have since begun working to stop it. Mayes' letter raises questions about the campus' power supply and the water used to generate that power.
What SpaceX has proposed
SpaceX has pledged $50 billion for what it calls its Cochise Supercomputer Campus, a hyperscale data center covering nearly 750 acres, according to AZFamily. The company's application to the county proposes nine buildings of 500,000 square feet each.
Antenori said SpaceX has addressed several of the county's concerns. Asked how he reacted when he learned the company was interested in Cochise County, he said: "I didn’t believe it." He added, "It was a big surprise. Hard to believe. And now it’s looking pretty good."
The jobs estimate
"When it’s fully built out, you’re probably looking at about a thousand jobs, half of which are likely going to be jobs that folks right out of high school can obtain," Antenori said. AZFamily reported that SpaceX originally put out the jobs estimate. ABC15 reported that the company anticipates about 5,500 construction jobs and 1,000 permanent jobs.
Antenori also said the project would bring 1,500 more secondary jobs. Greg Wright, a University of California, Merced professor who co-authored a Brookings Institution research paper on the topic, told AZFamily the roughly 1,000-job estimate was "plausible" for a campus this size but questioned the secondary figure. "That sounds a little high to me for a small rural community, but it could be something there," Wright said.
Both men said the county's finances could benefit. "It will definitely benefit our schools and our hospital districts, our fire districts and whatnot in the county," Antenori said.
What Mayes wants
In a Nov. 19 letter to the county Planning and Zoning Commission, Mayes said the county should let state and federal reviews finish before it rules on the project's Special Use Permit, AZFamily reported. SpaceX has proposed $3.6 billion in grid investments, AZFamily reported, but the letter says the company has given no details on how it will close a 4.5-gigawatt gap.
On water, AZFamily's account of the letter says the campus is dry-cooled and its application lists 7 to 10 acre-feet of use a year. The letter says that figure omits the water needed to generate the campus' power. The site lies within the Willcox Active Management Area, a zone the state designated to curb groundwater depletion.
What happens next
The commission must first approve the land use, AZFamily reported. The county then must work out a development agreement it says is legally binding, and the developer must get a building permit. The county estimates it could all be done by April or May.
AZFamily said it reached out to all nine commission members. Some had not heard of the letter or the request, and none said they would respond right away, the outlet reported. A county public information officer said the county has no new information to report.
Mayes will host a town hall at Cochise Elementary School on Thursday, Dec. 3, from 5:30 to 7 p.m., AZFamily reported. The commission is scheduled to discuss the permit application on Dec. 9, according to ABC15, the date The Chronicle reported Nov. 19.
Sources
Links to the reporting and records this story is based on.
- AZFamilyCochise County chair reveals what SpaceX promised for $50 billion data centerNov. 20, 2026
- AZFamilyAG Mayes asks Cochise County to delay vote on $50B SpaceX data centerNov. 19, 2026